Milestones identified for monitoring during the RGGVY Project execution for 11th plan period

 

Zero Date : Date of issue of Award to the Turnkey Contractor

Release of 1st Installment to the implementing agency- on readyness of award. (30% of project cost excluding the cost of BPL connections)



Qtr No End of Month Stipulated Milestone for Achievement
1 3 Submission of supply and work schedule by Turnkey contractor
  3 Establishment of site office
  3 Commencement of Survey
  3 Confirmation of PQCC that all MQP & FQP have been agreed as per Quality Manual
  3 Identification of land for substation
2 6 Survey completion - 50%
  6 Placement of orders for major items **
  6 Handing over of land for substation (Commencement)
3 8 Engagement of third party for Quality Monitoring
  9 Survey completion - 100% and submission of reports of quantity variation w.r.t. infrastructure requirement and deliverables (Villages and BPL Households)
  9 Completion of all engineering activities e.g. Finalisation of Technical Specifications, Approvals of sub-vendors/GTPs/Drawings etc.
  9 Installation of RGGVY display board (Commencement)
  9 Completion of Handing over of land for substations/ issue of NOC
  9 Commencement of inspection by RQM
  9 Commencement of supply of major items ** and completion of supply of material of the value of at least 25% of the total cost of material
  9 Finalisation of BPL list in consultation with the State Utility / State Govt. and its submission to REC
4 10 Start of pole erection
  10 Commencement of substation construction activities
  12 Start preparation for Franchisee arrangement
5 15 Achievement of 10% BPL households in electrified / un-electrified villages
  15 Achievement of minimum 10% un-electrified villages
6 18 Completion of dispatch of 75% of major items **
  18 Completion of 50% BPL connections in electrified / un-electrified villages
  18 Achievement of 50% un-electrified villages
7 20 Completion of supply of all major items **
8 22 Completion of Substation Construction including associated incoming line
  23 Commissioning of sub-stations
  23 Completion of arrangement of franchisee
  23 Achievement of 100% un-electrified villages
  23 Achievement of 100% BPL connections in un-electrified & electrified villages
  24 Completion of Energisation of Infrastructure
  24 Installation of RGGVY boards (Completion)
  24 Posting of details of infrastructure created in electrified / un-electrified villages on website


** Power Transformers, Distribution Transformers, Conductors, Poles, Insulators, LT Cables and Meters


Linkage of Payment To Milestones


2nd Installment : 
  1. Utilisation of 80% of 1st installment, Survey Completion and submission of reports of quantity variation w.r.to infrastructure requirement, and deliverables (Villages and BPL Households)

  2. Completion of all engineering activities e.g. Finalisation of Technical Specifications, Approvals of sub-vendors/ GTPs/Drawings etc.

3rd Installment : 
  1. Utilisation of 80% of 1st and 2nd installments

  2. Finalisation of BPL list in consultation with State Utility / State Govt. and its submission to REC

  3. Completion of works in minimum 10% un-electrified villages, release of minimum 10% BPL connections in electrified / un-electrified villages and submission of report by 3rd Party Inspection Agency to REC.